When a contract is silent, South Carolina's legal interest rate is 8.75% per year (S.C. Code Ann. § 34-31-20(A)). The details, including what you may agree to instead, are below with citations.

high confidenceFields we could not verify say so; nothing is guessed.

Default rate when the contract is silent

S.C. Code Ann. § 34-31-20(A)

8.75%per year

Attaches to the debt by operation of law when you agreed no rate, so it accrues before any lawsuit and can be stated on a demand letter.

8.75% per annum on accounts stated and sums ascertained that draw interest by law, in the absence of a written agreement setting a rate. Separately, § 34-31-20(B) sets post-judgment/money-decree interest at the WSJ prime rate (first edition of the calendar year) plus 4 percentage points, compounded annually. Verified on the official scstatehouse.gov site.

Agreed (contract) rates and caps

S.C. Code Ann. § 37-10-106

By express written agreement, any rate of interest may be charged - S.C. Code § 37-10-106 caps interest at 6% only on contracts NOT in writing; written contracts may specify any rate (South Carolina abolished general usury caps for written agreements in 1982). Consumer credit remains regulated by the SC Consumer Protection Code (Title 37, with maximum-rate-schedule filing for high-rate consumer creditors); B2B written contracts are effectively uncapped. Verify with counsel.

Prompt payment act

S.C. Code Ann. §§ 29-6-30, 29-6-50; § 11-35-45

public+private-construction

Construction (public and private): §§ 29-6-30/29-6-50 - periodic/final payments delayed more than 21 days (owner→contractor) or 7 days after receipt of funds (contractor→subcontractor) accrue interest at 1% per month, but only if the payee notified the payor of the statute at the time of the payment request; on private projects the parties may contract for different rates/periods if §§ 29-6-30 and 29-6-50 are specifically waived by section number in conspicuous bold/underlined type. State procurement: § 11-35-45 - vouchers due within 30 work days; the Comptroller General may levy up to 15% per year on the unpaid balance for the vendor. No general private commercial (non-construction) prompt-payment statute.

Late-fee notes

Distinctive rules actually found: the 1%/month construction late-payment interest requires advance notice of the statute at the time of the payment request, and private-project parties can opt out only via a conspicuous section-number waiver. Otherwise flat late fees on commercial invoices follow ordinary liquidated-damages/penalty doctrine.

Compute a late fee on a real invoice under South Carolina context, derivation shown, citation alongside.

Calculator, prefilled for SC

Sources for this entry

Not legal advice

Informational summary of state and federal statutes as researched on the sources listed per entry; not legal advice - verify current law with licensed counsel before relying on any rate or citation.

Nearby in the library

All states and the federal Prompt Payment Act →

Chasing invoices in South Carolina?

Duebay applies these rules automatically: fees computed from your agreed terms, the citation shown, and reminder sequences that escalate on schedule.